From 6 - 8:04:10 the House could be built. Work began at 6 clock

06/04/2010

6am - Trucks with house was already there, is from Hepp with the framework on the construction site and curses too little space, they would have built up the defense a few days rather

6:45 clock - Mounting column arrives on site and immediately begin the work

7:47 clock - The first wall is

8:55 clock - the outer walls and inner walls are on the ground floor, after that truck with the other parts unloaded

9:25 clock - truck with the roof and the rest of the material has arrived and is discharged, the roof is prepared

10:00 clock - in the meantime, the roof tiles have since been unloaded and

11:20 clock the ceiling beams are then placed by crane on ground

12:54 clock ceiling tiles will be installed first clock

15:34 gable wall will be attached

17:30 clock built chimney

17:41 clock prepared roof is fixed

17:48 2.Giebel clock is assembled

clock 17:55 rafters are laid

19:30 clock closing time Tag1


4/7/2010 Day 2

7am - roof construction is built

12:32 clock - the first tile

13:20 clock - when laying Room remember the men they have measured, so had some of the bricks are turned covers, took less than 15min

17:45 clock - the roof is covered, and clean up remaining work

18:45 clock - a day and our house is built and the 1 day earlier than planned!