Innenausbau - Lieferung und Beginn der Dämmung und Beplankung
today went on the interior. The Fa.Hepp was just before 8am on the site. The material was missing and so once all the tools and equipment were unloaded. About half past eight then came the first truck. A 20t with a lot of insulation to Board.Alles was parked and unloaded centrally. A short time later went off to work. An hour later, the next truck came with plasterboard to all walls and ceilings. By 14 clock came the last truck for today, had the window sills and mortar board.
worked until 20pm and tomorrow it starts again soon.